Welcome to Lower Bari Doab Canal Improvement Project (LBDCIP)

4.4 Participating Bidders and Summary of Bids

4.4.8 R&U of Sahiwal Distributary

PARTICIPATING BIDDERS, SUMMARY OF BID PRICES AND AWARD OF CONTRACT

Part 1: Invitation of Bids.

SR # Items Details
1 Contract Description Rehabilitation and Upgrading of Branch Canal and Distributary System covering Sahiwal Divison
2 Contract Number LBDC/ICB-05
3 Date of Issuance of Invitation for Bids 22 October 2011
4 Date of Deadline for Submission of Bids 20 December 2011

Part 2: Prequalified Bidders Invited to Submit the Bid

Sr # Contractors Invited to Submit Bid Amount of Bid in Pak Rupees Ranking Remarks
1 Khalid Rauf & Co.(Pvt) Ltd     Did not submit bid.
2 Descon Engineering Limited 8,397,084,827 2 Responsive Bidder.
3 Hydro Engineering Consortium     Did not submit bid.
4 NEIE-LAC (JV) 6,288,992,209 1 Lowest evaluated and responsive bidder.
5 Central China Power Group for International Economic and Trade Co. Ltd.     Did not submit bid.
6 China Liaoing International Economic & Technical Cooperation Group (CLIC), 6600,000,000   Non Responsive Bidder.
7 NEIE     Did not submit bid.


Part 3:Salient Features of Contract

Sr. # Item Details
1 Winning Bidder NEIE-LAC(JV)
2 Contract Cost Rs.6,288,992,209. Amended on 28 May 2014 to Rs.5,057,6040,53
3 Letter of Acceptance 04 August 2012.
4 Contract Signing 12 October 2012.
5 Notification Commencement of Work 31 December 2012
6 Completion Date 30 September 2015
7 Construction Period 1,003
Project Detail
News EMPLOYMENT OPPORTUNITIES IRRIGATION DEPARTMENT Project Management Unit for Lower Bari Doab Canal Improvement Project Lahore Dated-24-04-2016