4.4 Participating Bidders and Summary of Bids

4.4.1 R&U of Balloki Barrage


PARTICIPATING BIDDERS,SUMMARY OF BID PRICES AND AWARD OF CONTRACT


Part 1: Invitation of Bids.

SR # Items Details
1 Contract Description Rehabilitation and Upgrading of Balloki Barrage and Head Regulators
2 Contract Number BB/ICB-01
3 Date of Issuance of Invitation for Bids 30 September 2010
4 Date of Deadline for Submission of Bids 20 December 2010


Part 2: Pre-qualified Bidders Invited to submit the Bid.

Seven Bids were received from nine Pre-qualified bidders.

Sr # Contractors Invited to Submit Bid Amount of Bid in Pak Rupees Ranking Remarks
1 M/s China Liaoning International Economic & Technical Cooperation Group Corporation Ltd (CLIC)     Did not participate in Bidding.
2 M/s China International Water and Electric Corp. 3,078,017,854 5  
3 M/s Sinohydro Corporation Limited 4,227,987,934 7 Non-responsive to bid; not evaluated
4 M/s Ghulam Rasool & Company Pvt Ltd. (GRC) & Furthai Engineering Technology Dev. Co. 2,916,314,595 3  
5 M/s Chaudhary Engineers Associates & Central China Power Group International Economic & Trade Co Ltd (CCPG) 2,949,313,816 4 Non-responsive to bid; not evaluated;
6 M/s Descon Engineering Ltd. 3,249,766,711 6  
7 M/s Xinjiang Beixin Construction & Engineering (Group) Co Ltd & MATRACON 2,882,444,151 2  
8 M/s Saadullah Khan & Brothers (SKB) & JME 2,256,795,776 1 Lowest evaluated Bid
9 M/s North China International Electric Power Corporation (NEIE) & KNK Pvt. Ltd     Did not participate in Bidding.


Part 3:Salient Features of Contract.

Sr. # Item Details
1 Winning Bidder Saadullah Khan & Brothers (SKB) & JME Joint Venture
2 Contract Cost Rs.2,256,795,776
3 Letter of Acceptance 16 May 2011
4 Contract Signing 14 June 2011
5 Notification Commencement of Work 07 September 2011
6 Completion Date 04 September 2013 Extended to 06 Feb 2014
7 Construction Period 730 days Extended to 833 days