4.4 Participating Bidders and Summary of Bids

4.4.4 R&U of Main Canal-01, RD 0+000 to 227+454

PARTICIPATING BIDDERS, SUMMARY OF BID PRICES AND AWARD OF CONTRACT

Part 1: Invitation of Bids.

SR # Items Details
1 Contract Description Rehabilitation and Upgrading of Lower Bari Doab Canal (RD 0+000 to 227+454)
2 Contract Number LBDC/ICB-01
3 Date of Issuance of Invitation for Bids 25 June 2010
4 Date of Deadline for Submission of Bids 24 August 2010

Part 2: Prequalified Bidders Invited to Submit the Bid

Sr# Contractors Invited to Submit Bid Amount of Bid in Pak Rupees Ranking Remarks
1 SinohydroCorporation Limited 4,308,734,213 3  
2 Sambu Sachal Joint Venture     Did not submit bid
3 M/s SPARCO-CLIC Joint Venture     Did not submit bid
4 M/s Hydro Engineering Consortium 2,078,965,053 2  
5 M/s CFRG-BAL Joint Venture 11,201,821,444   Bid too high compared to others; not evaluated
6 M/s RMC Construction Company     Not responsive to bid; not evaluated
7 M/s Ghulam Rasool & Company (Pvt) Ltd 1,970,560,511 1 Lowest bid evaluated
8 M/s Ramzan & Sons     Did not submit bid


Part 3:Salient Features of Contract

Sr. # Item Details
1 Winning Bidder M/s Ghulam Rasool & Company (Pvt) Ltd
2 Contract Cost Rs.1,970,560,511
3 Letter of Acceptance 17 January 2011
4 Contract Signing 02 Feb 2011
5 Notification Commencement of Work 04 April 2011
6 Completion Date 29 Sept 2013
7 Construction Period 910 days
Project Detail
News EMPLOYMENT OPPORTUNITIES IRRIGATION DEPARTMENT Project Management Unit for Lower Bari Doab Canal Improvement Project Lahore Dated-24-04-2016